CMS: Requirements for mandatory annual state reporting of Medicaid Core Sets of Quality Measures

09.15.23

What Medicaid agencies and Medicaid-participating managed care organizations need to know about new mandatory federal requirements for reporting on the core sets of quality measures.

Read this if you administer a Medicaid agency, a CHIP program, or a Medicaid-participating managed care organization. 

On August 31, 2023, the Centers for Medicare & Medicaid Services (CMS) issued its Final Rule, which establishes requirements for mandatory annual state reporting of the following Core Sets of Medicaid quality measures:

  • The Core Set of Children’s Health Care Quality Measures for Medicaid and the Children’s Health Insurance Program (CHIP)
  • The behavioral health measures on the Core Set of Adult Health Care Quality Measures for Medicaid
  • The Core Sets of Health Home Quality Measures for Medicaid  
  • The regulations associated with the Final Rule are effective January 1, 2024. The initial (2024) round of reporting must be submitted and certified by states by December 31, 2024


FAQs: Medicaid Core Sets reporting requirements  

  • Do these reporting requirements apply exclusively to the 50 states? 
    No. These requirements include the 50 states, the District of Columbia, Puerto Rico, the Virgin Islands, and Guam. American Samoa and the Mariana Islands could, but would not be required to, report Child Core Set and Adult Core Set measures. 
  • Do all Medicaid agencies operate health home programs?
    No. “Health homes” refers to two optional Medicaid benefits that states may elect to implement through their CMS State Plan Amendment (SPA). The Section 1945 health home benefit is for Medicaid-eligible individuals who have: a) two or more chronic conditions; b) at least one chronic condition and who are at risk of developing a second; or c) at least one serious and persistent mental health condition. The Section 1945A health home benefit is for Medicaid-eligible children with medically complex conditions. 
  • If a state’s CHIP is separate from the Medicaid program, do these reporting requirements also apply to CHIP? 
    Yes. The Medicaid agency must report on the measures for standalone CHIP-enrolled beneficiaries in addition to Medicaid-enrolled beneficiaries, according to each measure’s age range specifications. 
  • Are Medicaid agencies required to report on all Medicaid and CHIP beneficiaries, including those enrolled in fee-for-service and managed care?
    Yes. However, the Secretary of HHS could specify in CMS’ annual reporting guidance that a population is not required to be included. Also, the Secretary could grant a Medicaid agency an exemption from reporting on one or more measures for a specific population.
  • Is there a filing deadline for a Medicaid agency to request a reporting exemption?
    Yes. A request for an exemption must be submitted by September 1 of the applicable reporting year. A Medicaid agency may request a one-year exemption from reporting for a specific population. This request must demonstrate that the Medicaid agency is unable to obtain access to data required to report the measures for a population despite making reasonable efforts to do so. The request must also document a reasonable timeline of actions underway to resolve data access problems.
  • Will these requirements require a Medicaid agency to submit a change in its state plan? 
    Yes. The Medicaid agency must submit a state plan amendment, specifying that it will report on the Child Core Sets and Adult Core Sets in accordance with 42 CFR § 437.15.

    If the Medicaid agency offers either or both of the optional health home services, then the state plan will need to also address the health home reporting requirements in accordance with 42 CFR § 437.15. The Medicaid agency must also require health home service providers to report to the agency on all populations served by the health home provider and on the measures in the applicable Health Home Core Set as a condition of receiving payment for these services.
  • Can CMS withhold federal Medicaid payments, in whole or part, from a state that is non-compliant with these reporting requirements? 
    Yes. CMS has stated that graduated enforcement mechanisms for compliance with Core Sets reporting requirements due to issues with state data systems will align with existing CMS policy regarding state corrective action plans.
  • Will CMS modify the Core Sets measures on an annual basis?
    Yes. The Secretary of HHS will identify and annually update the quality measures beginning no later than January 1, 2024, and annually no later than January 1 thereafter. In issuing the annual guidance, the Secretary may consider the level of difficulty in accessing the data required for reporting and may provide that reporting will be voluntary for a specific year. 
  • Will CMS establish data stratification rules for these measures? 
    Yes. In considering which measures, and by which factors (such as race, ethnicity, sex, age, rural/urban status, disability, language, or other factors) states must report stratified measures, the Secretary of HHS will consider whether stratification can be accomplished based on valid statistical methods. Other considerations include whether stratification will not risk a violation of beneficiaries’ privacy and whether the original survey instrument collects the variables necessary to stratify the measures. The rollout of stratification requirements will begin by the second year of annual reporting after the effective date of these regulations and increase yearly. By the fifth year of annual reporting after the effective date of these regulations, 100% of measures will be stratified.      
  • Will CMS make the reporting information publicly available? 
    Yes. CMS will make the Core Sets information publicly available not later than September 30, 2025, and annually by September 30 thereafter. 

Centers for Medicare & Medicaid Services Core Set resources

If you have questions about the Core Measure Sets for Medicaid or need guidance in complying with these reporting requirements, please contact Robyn Hoffmann or Ethan Wiley.

Related Industries

Related Services

Accounting and Assurance

Consulting

Business Advisory

Related Professionals

BerryDunn experts and consultants

Editor’s note: If you are a state government CFO, CIO, project or program manager, this blog is for you. 

This is the second blog post in the blog series: “Procuring Agile vs. Non-Agile Service”. Read the first blog. This blog post demonstrates the differences in Stage 1: Plan Project in the five stages of procuring agile vs. non-agile services.

Overview of Procurement Process for Agile vs. Non-Agile IT Services

What is important to consider in agile procurement?

Here are some questions that can help focus the planning for procurement of IT services for agile vs. non-agile projects.

Plan Project Considerations for Agile vs. Non-Agile IT Services

Why are these considerations important?

When you procure agile IT services, you can define the scope of your procurement around a vision of what your organization intends to become, as opposed to being restricted to an end-date for a final delivery.

In an agile project, you get results iteratively; this allows you to constantly reassess requirements throughout the project, including the project plan, the guiding principles, and the project schedule. Your planning is not restricted to considering the effect of one big result at the end of the project schedule. Instead, your plan allows for sequencing of changes and improvements that best reflect the outcomes and priorities your organization needs

Since planning impacts the people-aspect of your strategy, it is important to consider how various teams and stakeholders will provide input, and how you will make ongoing communication updates throughout the project. With an agile procurement project, your culture will shift, and you will need a different approach to planning, scheduling, communicating, and risk management. You need to communicate daily, allowing for reviewing and adjusting priorities and plans to meet project needs. 

How do you act on these considerations?

A successful procurement plan of agile IT services should include the following steps:

  1. Develop a project charter and guiding principles for the procurement that reflect a vision of how your organization’s teams will work together in the future
  2. Create a communication plan that includes the definition of project success and communicates project approach
  3. Be transparent about the development strategy, and outline how iterations are based on user needs, that features will be re-prioritized on an ongoing basis, and that users, customers, and stakeholders are needed to help define requirements and expected outcomes
  4. Provide agile training to your management, procurement, and program operation teams to help them accept and understand the project will present deliverables in iterations, to include needed features, functionality and working products
  5. Develop requirements for the scope of work that align with services and outcomes you want, rather than documented statements that merely map to your current processes 

What’s next? 

Now that you have gained insight into the approach to planning an agile project, consider how you may put this first stage into practice in your organization. Stay tuned for guidance on how to execute the second stage of the procurement process—how to draft the RFP. Our intention is that, following this series, your organization will better understand how to successfully procure and implement agile services. If you have questions or comments, please contact our team.
 

Article
Plan agile projects: Stage 1

Read this if you are a State Medicaid Director, State Medicaid Chief Information Officer, State Medicaid Project Manager, or State Procurement Officer—or if you work on a State Medicaid Enterprise System (MES) certification effort.

Measuring performance of Medicaid Enterprise Systems (MES) is emerging as the next logical step in moving Medicaid programs toward modularity. As CMS continues to refine and implement outcomes-based modular certification, it is critical that states adapt to this next step in order to continue to meet CMS funding requirements.

This measurement, in terms of program outcomes, presents a unique set of challenges, many of which a state may not have considered before. A significant challenge is determining how and where to begin measuring program outcomes―to meet it, states can leverage a trusted, independent partner as they undertake an outcomes-based effort.

Outcomes-based planning can be thought of as a three-step process. First, and perhaps most fundamental, is to define outcomes. Second, you need to determine what measurements will demonstrate progress toward achieving those outcomes. And the final step is to create reporting measurements and their frequency. Your independent partner can help you answer these critical questions and meet CMS requirements efficiently by objectively guiding you toward realizing your goals.

  1. Defining Outcomes
    When defining an outcome, it is important to understand what it is and what it isn’t. An outcome is a benefit or added value to the Medicaid program. It is not an output, which is a new or enhanced function of a new MES module. An output is the product that supports the outcome. For example, the functionality of a new Program Integrity (PI) module represents an output. The outcome of the new PI module could be that the Medicaid program continuously improves based on data available because of the new PI module. Some outcomes may be intuitive or obvious. Others may not be as easy to articulate. Regardless, you need to direct the focus of your state and solution vendor teams on the outcome to uncover what the underlying goal of your Medicaid program is.
     
  2. Determining Measurements
    The second step is to measure progress. Well-defined Key Performance Indicators (KPIs) will accurately capture progress toward these newly defined outcomes. Your independent partner can play a key role by posing questions to help ensure the measurements you consider align with CMS’ goals and objectives. Additionally, they can validate the quality of the data to ensure accuracy of all measurements, again helping to meet CMS requirements.
     
  3. Reporting Measurements
    Finally, your state must decide how―and how often―to report on outcomes-based measurements. Your independent partner can collaborate with both your state and CMS by facilitating conversations to determine how you should report, based on a Medicaid program’s nuances and CMS’ goals. This can help ensure the measurements (and support information) you present to CMS are useful and reliable, giving you the best chance for attaining modular certification.

Are you considering an outcomes-based CMS modular certification, or do you have questions about how to best leverage an independent partner to succeed with your outcomes-based modular certification effort? BerryDunn’s extensive experience as an independent IV&V and Project Management Office (PMO) partner includes the first pilot outcomes-based certification effort with CMS. Please visit our IV&V and certification experts at our booth at MESC 2019 or contact our team now.

Article
Three steps to measure Medicaid Enterprise Systems outcomes

Read this if you are a State Medicaid Director, State Medicaid Chief Information Officer, State Medicaid Project Manager, or State Procurement Officer.

As CMS moves away from the monolithic Medicaid Management Information System (MMIS) toward an outcomes-based approach that includes a modular Medicaid Enterprise System (MES), there is now more emphasis on system integration (SI). 

In the August 16, 2016 letter, State Medicaid Director (SMD) #16-010, CMS clarified the role of the system integrator (SI) by stating:

CMS envisions a discrete role for the system integrator (SI) in each state, with specific focus on ensuring the integrity and interoperability of the Medicaid IT architecture and cohesiveness of the various modules incorporated into the Medicaid enterprise. 

While the importance of the SI role is apparent, not all states have the resources to build the SI capability within their own organizations. Some state Medicaid IT teams try to solve this by delegating management roles to vendors or contractors. This approach has various risks. A state could lose:

  • Institutional knowledge, as vendors and contractors transition off the project
  • Control of governance, oversight, and leadership
  • The ability to enforce contractual requirements across each vendor, especially the SI

In addition, the ramifications of loss of state accountability can have wide-reaching implementation, operational, and financial impacts, including:

  • The loss of timely decision making, causing projects to fall behind schedule
  • State-specific policy needs not being met, impacting how the MMIS functions in production 
  • Poor integration into the state-specific Operation and Maintenance (O&M) support model, increasing the state’s portion of long-term O&M costs
  • Inefficient and ineffective contract management of each module vendor and contractor (including the SI), possibly leading to unneeded change requests and cost overruns
  • Lack of coordination with the state’s business or IT roadmap initiatives (i.e., system consolidation or cloud migration vendor/approach), possibly leading to rework and missed opportunities to reduce cost or improve interoperability 

Apply strong governance and IV&V to tackle risks

Because the SI vendor is responsible for the integration of multiple modules across multiple vendors, you may consider delegating oversight of module vendors to the SI vendor. 

The major benefit states get from using the SI vendor is efficiency. Having your vendor as the central point of contact can quickly resolve technical issues, while allowing easy coordination of project tasks across each module vendor on a continual basis. 

If you choose to use a vendor for the SI role, establish safeguards and governance to make sure your goals are being met:

  • Build a project-specific governance model (executive committee [EC]) to oversee the vendors and the project
  • Establish a regular meeting cadence for the EC to allow for status updates on milestones and discuss significant project risks and issues 
  • Allocate state resources into project leadership roles (i.e., project manager, vendor contract manager, security lead, testing/Quality Assurance lead, etc.)
  • Conduct regular (weekly) SI status meetings to track progress and address risks and issues 

You also need a strong, involved governance structure that includes teams of state senior leadership, state program managers, SI vendor engagement/contract managers, and Independent Verification and Validation (IV&V) vendors. By definition, one responsibility of IV&V is to identify and monitor project risks and issues that could arise from a lack of independence. 

Your governance teams can debate decisions and disputes, risks and issues, and federal compliance issues with their vendors to define direction and action plans. However, a state representative within these teams should always make the final management decisions, approve all SI scope items and changes, and approve all contractual deliverables from each vendor or contractor.

Your state staff (business and IT) provides project management decision, business needs, requirements (functional and non-functional), policy guidance, and continuity as the vendors and/or contractors change over time. 

The conclusion? In order to be successful, you must retain certain controls and expertise to deploy and operate a successful MMIS system. Our consultants understand the need to keep you in control of managing key portions of implementation projects/programs and operational tasks. If you have questions, please contact BerryDunn’s Medicaid team.  
 

Article
Risks when using vendors to manage Medicaid system implementation projects

Read this if you are a state Medicaid Director, State Medicaid Chief Information Officer, State Medicaid Project Manager, or State Procurement Officer.

When I was growing up, my dad would leave the Bureau of Motor Vehicles or hang up the phone after talking with the phone company and say sarcastically, “I’m from the government (or the phone company) and I’m here to help you. Yeah, right.” I could hear the frustration in his voice. As I’ve gotten older, I understand the hassle of dealing with bureaucracy, where the red tape can make things more difficult than they need to be, and where customers don’t come first. It doesn’t have to be that way.

In my role performing Independent Verification and Validation (IV&V) at BerryDunn, I hear the same skepticism in the voices of some of my clients. I can hear them thinking, “Let me get this straight… I’m spending millions of dollars to replace my old Medicaid Management Information System (MMIS), and the Centers for Medicare and Medicaid Services (CMS) says I have to hire an IV&V consultant to show me what I am doing wrong? I don’t even control the contract. You’re here to help me? Yeah, right.” Here are some things to assuage your doubt. 

Independent IV&V―what they should do for you and your organization

An independent IV&V partner that is invested in your project’s success can:

  • Enhance your system implementation to help you achieve compliance
  • Help you share best practice experience in the context of your organization’s culture to improve efficiency in other areas
  • Assist you in improving your efficiency and timeliness with project management capabilities.

Even though IV&V vendors are federally mandated from CMS, your IV&V vendor should also be a trusted partner and advisor, so you can achieve compliance, improve efficiency, and save time and effort. 

Not all IV&V vendors are equal. Important things to consider:

Independence―independent vendors are a good place to start, as they are solely focused on your project’s success. They should not be selling you software or other added services, push vendor affiliations, or rubber stamp CMS, nor the state. You need a non-biased sounding board, a partner willing to share lessons learned from experience that will help your organization improve.

Well-rounded perspective―IV&V vendors should approach your project from all perspectives. A successful implementation relies on knowledge of Medicaid policy and processes, Medicaid operations and financing, CMS certification, and project management.

“Hello, we are IV&V from BerryDunn, and we are here to help.”

BerryDunn offers teams that consist of members with complementary skills to ensure all aspects of your project receive expert attention. Have questions about IV&V? Contact our team.
 

Article
We're IV&V and we are here to help you improve your Medicaid organization

As the Project Management Body of Knowledge® (PMBOK®) explains, organizations fall along a structure and reporting spectrum. On one end of this spectrum are functional organizations, in which people report to their functional managers. (For example, Finance staff report to a Finance director.) On the other end of this spectrum are projectized organizations, in which people report to a project manager. Toward the middle of the spectrum lie hybrid—or matrix—organizations, in which reporting lines are fairly complex; e.g., people may report to both functional managers and project managers. 

Problem: Weak Matrix Medicaid System Vendors

This brings us to weak matrix organizations, in which functional managers have more authority than project managers. Many Medicaid system vendors happen to fall into the weak matrix category, for a number of different reasons. Yet the primary factor is the volume and duration of operational work—such as provider enrollment, claims processing, and member enrollment—that Medicaid system vendors perform once they exit the design, development, and implementation (DDI) phase.

This work spans functional areas, which can muddy the reporting waters. Without strong and clear reporting lines to project managers, project success can be seriously (and negatively) affected if the priorities of the functional leads are not aligned with those of the project. And when a weak matrix Medicaid system vendor enters a multi-vendor environment in which it is tasked with implementing a system that will serve multiple departments and bureaus within a state government, the reporting waters can become even muddier.


Solution: Using a Project Management Office (PMO) Vendor

Conversely, consulting firms that provide Project Management Office (PMO) services to government agencies tend to be strong matrix organizations, in which project managers have more authority over project teams and can quickly reallocate team members to address the myriad of issues that arise on complex, multi-year projects to help ensure project success. PMOs are also typically experienced at creating and running project governance structures and can add significant value in system implementation-related work across government agencies.

Additional benefits of a utilizing a PMO vendor include consistent, centralized reporting across your portfolio of projects and the ability to quickly onboard subject matter expertise to meet program and project needs. 
For more in-depth information on the benefits of using a PMO on state Medicaid projects, stay tuned for my second blog in this series. In the meantime, feel free to send your PMO- or Medicaid-related questions to me
 

Article
The power of the PMO: Fixing the weak matrix

As your organization works to modernize and improve your Medicaid Enterprise System (MES), are you using independent verification and validation (IV&V) to your advantage? Does your relationship with your IV&V provider help you identify high-risk project areas early, or provide you with an objective view of the progress and quality of your MES modernization initiative? Maybe your experience hasn’t shown you the benefits of IV&V. 

If so, as CMS focuses on quality outcomes, there may be opportunities for you to leverage IV&V in a way that can help advance your MES to increase the likelihood of desired outcomes for your clients. 

According to 45 Code of Federal Regulations (CFR) § 95.626, IV&V may be required for Advanced Planning Document (APD) projects that meet specific criteria. That said, what is the intended role and benefit of IV&V? 

To begin, let’s look at the meaning of “verification” and “validation.” The Institute of Electrical and Electronics Engineers, Inc. (IEEE) Standard for Software Verification and Validation (1012-1998) defines verification as, “confirmation of objective evidence that the particular requirements for a specific intended use are fulfilled.” Validation is “confirmation of objective evidence that specified requirements have been fulfilled.” 

Simply put, verification and validation ensure the right product is built, and the product is built right. 
As an independent third party, IV&V should not be influenced by any vendor or software application. This objectivity means IV&V’s perspective is focused on benefiting your organization. This support includes: 

  • Project management processes and best practices support to help increase probability of project success
  • Collaboration with you, your vendors, and stakeholders to help foster a positive and efficient environment for team members to interact 
  • Early identification of high-risk project areas to minimize impact to schedule, cost, quality, and scope 
  • Objective examination of project health in order for project sponsors, including the federal government, to address project issues
  • Impartial analysis of project health that allows state management to make informed decisions 
  • Unbiased visibility into the progress and quality of the project effort to increase customer satisfaction and reduce the risk and cost of rework
  • Reduction of errors in delivered products to help increase productivity of staff, resulting in a more efficient MES 

Based on our experience, when a trusted relationship exists between state governments and IV&V, an open, collaborative dialogue of project challenges—in a non-threatening manner—allows for early resolution of risks. This leads to improved quality of MES outcomes.    

Is your IV&V provider helping you advance the quality of your MES? Contact our team.

Article
Leveraging IV&V to achieve quality outcomes

Editor’s note: If you are a state government CFO, CIO, project or program manager, this blog is for you.

What is the difference in how government organizations procure agile vs. non-agile information technology (IT) services? (Learn more about agile here).

In each case, they typically follow five stages through the process as shown in Figure A:
 

Figure A: Overview of Procurement Process for Agile vs. Non-Agile IT Services

However, there are differences in how these stages are carried out if procuring agile vs. non-agile IT services. 

Unfortunately, most government organizations are unaware of these differences, which could result in unsuccessful procurements and ultimately not meeting your project’s needs and expectations. 
This blog series will illustrate how to strategically adjust the standard stages outlined in Figure A to successfully procure agile IT services.

Stage 1: Plan project
In Stage 1, you define the scope of the project by identifying what your organization wants, needs, and can achieve within the available timeframe and budget. You then determine the project’s objectives while strategically considering their impact on your organization before developing the RFP. Figure B summarizes the key differences between the impacts of agile vs. non-agile services to consider in this stage.


Figure B: Plan Project for Agile vs. Non-Agile IT Services

The nuances of planning for agile services reflect an organization’s readiness for a culture shift to a continuous process of development and deployment of software and system updates. 

Stage 2: Draft RFP
In Stage 2, as part of RFP drafting, define the necessary enhancements and functionality needed to achieve the project objectives determined in Stage 1. You then translate these enhancements and functionalities into business requirements. Requirement types might include business needs as functionality, services, staffing, deliverables, technology, and performance standards. Figure C summarizes the key differences between drafting the RFP for a project procuring agile vs. non-agile services.


Figure C: Draft RFP for Agile vs. Non-Agile IT Services

In drafting the RFP, the scope of work emphasizes expectations for how your team and the vendor team will work together, the terms of how progress will be monitored, and the description of requirements for agile tools and methods.

Stage 3: Issue RFP
In Stage 3, issue the RFP to the vendor community, answer vendor questions, post amendments, and manage the procurement schedule. Since this stage of the process requires you to comply with your organization’s purchasing and procurement rules, Figure D illustrates very little difference between issuing an RFP for a project procuring agile or non-agile services.


Figure D: Issue RFP for Agile vs. Non-Agile IT Services 

Stage 4: Review proposals
In Stage 4, you evaluate vendor proposals against the RFP’s requirements and project objectives to determine the best proposal response. Figure E summarizes the key differences in reviewing proposals for a project that is procuring agile vs. non-agile services.


Figure E: Reviewing Proposals for Agile vs. Non-Agile IT Services 

Having appropriate evaluation priorities and scoring weights that align with how agile services are delivered should not be under-emphasized. 

Stage 5: Award and implement contract
In Stage 5, you award and implement the contract with the best vendor proposal identified during Stage 4. Figure F summarizes the key differences in awarding and implementing the contract for agile vs. non-agile services.


Figure F:  Award and Implement Contract for Agile vs. Non-Agile Services 

Due to the iterative and interactive requirements of agile, it is necessary to have robust and frequent collaboration among program teams, executives, sponsors, and the vendor to succeed in your agile project delivery.

What’s next?
The blog posts in this series will explain step-by-step how to procure agile services through the five stages, and at the series conclusion, your organization will better understand how to successfully procure and implement agile services. If you have questions or comments, please contact our team.  

Article
Procuring agile vs. non-agile projects in five stages: An overview