Success by steering committee

11.29.17

Most of us have been (or should have been) instructed to avoid using clichés in our writing. These overstated phrases and expressions add little value, and often only increase sentence length. We should also avoid clichés in our thinking, for what we think can often influence how we act.

Consider, for example, “death by committee.” This cliché has greatly — and negatively — skewed views on the benefits of committees in managing projects. Sure, sometimes committee members have difficulty agreeing with one another, which can lead to delays and other issues. In most cases, though, an individual can’t possibly oversee all aspects of a project, or represent all interests in an organization. Committees are vital for project success — and arguably the most important project committee is the steering committee.

What Exactly is a Steering Committee?
It is a group of high-level stakeholders that provides strategic direction for a project, and supports the project manager. Ideally, the group increases the chances for project success by closely aligning project goals to organizational goals. However, it is important to point out that the group’s top priority is project success.

The committee should represent the different departments and agencies affected by the project, but remain relatively small in size, chaired by someone who is not an executive sponsor of the project (in order to avoid conflicts of interest). While the project manager should serve on the steering committee, they should not participate in decision-making; the project manager’s role is to update members on the project’s progress, areas of concern, current issues, and options for addressing these issues.

Overall, the main responsibilities of a steering committee include:

  1. Approving the Project Charter
  2. Resolving conflicts between stakeholder groups
  3. Monitoring project progress against the project management plan
  4. Fostering positive communicating about the project within the organization
  5. Addressing external threats and issues emerging outside of the project that could impact it
  6. Reviewing and approving changes made to the project resource plan, scope, schedules, cost estimates, etc.

What Are the Pros and Cons of Utilizing a Steering Committee?
A group of executive stakeholders providing strategic direction should benefit any project. Because steering committee members are organizational decision-makers, they have the access and credibility to address tough issues that can put the project at a risk, and have the best opportunities to negotiate positive outcomes. In addition, steering committees can engage executive management, and make sure the project meshes with executive management’s vision, mission, and long-range strategic plan. Steering committees can empower project managers, and ensure that all departments and agencies are on the same page in regards to project status, goals, and expectations. In a 2009 article in Project Management Journal, authors Thomas G. Lechler and Martin Cohen concluded that steering committees are important to implementing and maintaining project management standards on an operational level — not only do steering committees directly support project success, they are instrumental in deriving value from an organization's investments in its project management system.

A steering committee is only as effective as it’s allowed to be. A poorly structured steering committee that lacks formal authority, clear roles, and clear responsibilities can impede the success of a project by being slow to respond to project issues. A proactive project manager can help the organization avoid this major pitfall by helping develop project documents, such as the governance document or project plan that clearly define the steering committee structure, roles, responsibilities and authority.

Steer Toward Success!
Steering committees can benefit your organization and its major projects. Yet understanding the roles and responsibilities — and pros and cons — is only a preliminary step in creating a steering committee. Need some advice on how to organize a steering committee? Want to learn more about steering committee best practices? Together, we can steer your project toward success.

Related Services

Consulting

Information Systems

There’s a good chance that your organization is in the position of needing to do more with less under the strain of staffing constraints and competing initiatives. With fewer resources to work with, you’ll need to be persuasive to get the green light on new enterprise technology initiatives. To do that, you need to present decision makers with well-thought-out and targeted business cases that show your initiative will have impact and will be successful. Yet developing such a business case is no walk in the park. Perhaps because our firm has its roots in New England, we sometimes compare this process to leading a hiking trip into the woods—into the wild. 

Just as in hiking, success in developing a business case for a new initiative boils down to planning, preparation, and applying a few key concepts we’ve learned from our travels. 

Consensus is critical when planning new technology initiatives

Before you can start the hike, everyone has to agree on some fundamentals: 

Who's going? 

Where are we going? 

When do we go and for how long? 

Getting everyone to agree requires clear communication and, yes, even a little salesmanship: “Trust me. The bears aren’t bad this time of year.” The same principle applies in proposing new technology initiatives; making sure everyone has bought into the basic framework of the initiative is critical to success.

Although many hiking trips involve groups of people similar in age, ability, and whereabouts, for your business initiative you need to communicate with diverse groups of colleagues at every level of the organization. Gaining consensus among people who bring a wide variety of skills and perspectives to the project can be complex.

To gain consensus, consider the intended audiences of your message and target the content to what will work for them. It should provide enough information for executive-level stakeholders to quickly understand the initiative and the path forward. It should give people responsible for implementation or who will provide specific skills substantive information to implement the plan. And remember: one of the most common reasons projects struggle to meet their stated objectives (and why some projects never materialize to begin with), is a lack of sponsorship and buy-in. The goal of a business case is to gain buy-in before project initiation, so your sponsors will actively support the project during implementation. 

Set clear goals for your enterprise technology project 

It’s refreshing to take the first steps, to feel that initial sense of freedom as you set off down the trail. Yet few people truly enjoy wandering around aimlessly in the wilderness for an extended period of time. Hikers need goals, like reaching a mountain peak or seeing famous landmarks, or hiking a predetermined number of miles per day. And having a trail guide is key in meeting those goals. 

For a new initiative, clearly define goals and objectives, as well as pain points your organization wishes to address. This is critical to ensuring that the project’s sponsors and implementation team are all on the same page. Identifying specific benefits of completing your initiative can help people keep their “eyes on the prize” when the project feels like an uphill climb.

Timelines provide additional detail and direction—and demonstrate to decision makers that you have considered multiple facets of the project, including any constraints, resource limitations, or scheduling conflicts. Identifying best practices to incorporate throughout the initiative enhances the value of a business case proposition, and positions the organization for success. By leveraging lessons learned on previous projects, and planning for and mitigating risk, the organization will begin to clear the path for a successful endeavor. 

Don’t compromise on the right equipment

Hiking can be an expensive, time-consuming hobby. While the quality of your equipment and the accuracy of your maps are crucial, you can do things with limited resources if you’re careful. Taking the time to research and purchase the right equipment, (like the right hiking boots), keeps your fun expedition from becoming a tortuous slog. 

Similarly, in developing a business case for a new initiative, you need to make sure that you identify the right resources in the right areas. We all live with resource constraints of one sort or another. The process of identifying resources, particularly for funding and staffing the project, will lead to fewer surprises down the path. As many government employees know all too well, it is better to be thorough in the budget planning process than to return to authorizing sources for additional funding while midstream in a project. 

Consider your possible outcomes

You cannot be too singularly focused in the wild; weather conditions change quickly, unexpected opportunities reveal themselves, and being able to adapt quickly is absolutely necessary in order for everyone to come home safely. Sometimes, you should take the trail less traveled, rest in the random lean-to that you and your group stumble upon, or go for a refreshing dip in a lake. By focusing on more than just one single objective, it often leads to more enjoyable, safe, and successful excursions.

This type of outlook is necessary to build a business case for a new initiative. You may need to step back during your initial planning and consider the full impact of the process, including on those outside your organization. For example, you may begin to identify ways in which the initiative could benefit both internal and external stakeholders, and plan to move forward in a slightly new direction. Let’s say you’re building a business case for a new land management and permitting software system. Take time to consider that this system may benefit citizens, contractors, and other organizations that interact with your department. This new perspective can help you strengthen your business case. 

Expect teamwork

A group that doesn’t practice teamwork won’t last long in the wild. In order to facilitate and promote teamwork, it’s important to recognize the skills and contributions of each and every person. Some have a better sense of direction, while some can more easily start campfires. And if you find yourself fortunate enough to be joined by a truly experienced hiker, make sure that you listen to what they have to say.

Doing the hard work to present a business case for a new initiative may feel like a solitary action at times, but it’s not. Most likely, there are other people in your organization who see the value in the initiative. Recognize and utilize their skills in your planning. We also suggest working with an experienced advisor who can leverage best practices and lessons learned from similar projects. Their experience will help you anticipate potential resistance and develop and articulate the mitigation strategies necessary to gain support for your initiative.

If you have thoughts, concerns, or questions, contact our team. We love to discuss the potential and pitfalls of new initiatives, and can help prepare you to head out into the wild. We’d love to hear any parallels with hiking and wilderness adventuring that you have as well. Let us know! 

BerryDunn’s local government consulting team has the experience to lead technology planning initiatives and develop actionable plans that help you think strategically and improve service delivery. We partner with you, maintaining flexibility and open lines of communication to help ensure that your team has the resources it needs.

Our team has broad and deep experience partnering with local government clients across the country to modernize technology-based business transformation projects and the decision-making and planning efforts. Our expertise includes software system assessments/planning/procurement and implementation project management; operational, management, and staffing assessments; information security; cost allocation studies; and data management.  

Article
Into the wild: Building a business case for a new enterprise technology project

Read this if your organization is planning on upgrading or replacing an enterprise technology system.

It can be challenging and stressful to plan for technology initiatives, especially those that involve and impact every area of your organization. Common initiatives include software upgrades or replacements for:

  • Financial management, such as Enterprise Resource Planning (ERP) systems
  • Asset management systems
  • Electronic health records (EHR) systems
  • Permitting and inspections systems

Though the number of considerations when planning enterprise technology projects can be daunting, the greatest mistake you can make is not planning at all. By addressing just a few key areas, you can avoid some of the most common pitfalls, such as exceeding budget and schedule targets, experiencing scope creep, and losing buy-in among stakeholders. Here are some tips to help you navigate your next project:

Identify your IT project roles and resources

While most organizations understand the importance of identifying project stakeholder groups, it is often an afterthought. Defining these roles at the outset of your project helps you accurately estimate the work effort.

Your stakeholder groups may include:

  • An executive sponsor
  • A steering committee
  • A project manager
  • Functional leads
  • A technical team

Once you’ve established the necessary roles, you can begin reviewing your organization’s resources to determine the people who will be available to fill them. Planning for resource availability will help you avoid delays, minimize impact to regular business processes, and reduce the likelihood of burnout. But this plan won’t remain static—you can expect to make updates throughout the project.

Establish clear goals and objectives to keep your technology project on track

It’s important that an enterprise technology project has established goals and objectives statements. These statements will help inform decision-making, provide benchmarks for progress, and measure your project’s success. They can then be referenced when key stakeholders have differing perspectives on the direction to take with a pending decision. For example, if the objective of your project is to reduce paper-based processes, you may plan for additional computer workstations and focus technical resources on provisioning them. You’ll also be able to measure your success in the reduction of paper-based tasks.

Estimate your IT project budget accurately

Project funding is hardly ever overlooked, but can be complex with project budgets that are either underestimated or estimated without sufficient rationale to withstand approval processes and subsequent budget analysis. You may find that breaking down estimates to a lower level of detail helps address these challenges. Most technology projects incur costs in three key areas:

  • Vendor cost: This could include both one-time software implementation costs as well as recurring costs for maintenance and ongoing support.
  • Infrastructure cost: Consider the cost of any investments needed to support your project, such as data center hardware, networking components, or computing devices.
  • Supplemental resource cost: Don’t forget to include the cost of any additional resources needed for their specialized knowledge or to simply backfill project staff. This could include contracted resources or the additional cost of existing resources (i.e., overtime).

A good technology project budget also includes a contingency amount. This amount will depend on your organization’s standards, the relative level of confidence in your estimates, and the relative risk.

Anticipate the need for change management

Depending on the project, staff in many areas of your organization will be impacted by some level of change during a technology implementation. External stakeholders, such as vendors and the public, may also be affected. You can effectively manage this change by proactively identifying areas of likely change resistance and creating strategies to address them.

In any technology implementation, you will encounter change resistance you did not predict. Having strategies in place will help you react quickly and effectively. Some proven change management strategies include communicating throughout your project, involving stakeholders to get their buy-in, and helping ensure management has the right amount of information to share with their employees.

Maintain focus and stay flexible as you manage your IT project

Even with the most thought-out planning, unforeseen events and external factors may impact your technology project. Establish mechanisms to regularly and proactively monitor project status so that you can address material risks and issues before their impact to the project grows. Reacting to these items as they arise requires key project stakeholders to be flexible. Key stakeholders must recognize that new information does not necessarily mean previous decisions were made in error, and that it is better to adapt than to stick to the initial direction.

Whether you’re implementing an ERP, an EHR, or enterprise human resources or asset management systems, any enterprise technology project is a massive undertaking, involving significant investment and a coordinated effort with individuals across multiple areas of an organization. Common mistakes can be costly, but having a structured approach to your planning can help avoid pitfalls. Our experienced, objective advisors have worked with public and private organizations across the country to oversee large enterprise projects from inception to successful completion.

Contact our software consulting team with any questions.

Article
Planning for a successful enterprise technology project

Read this if you are a leader at a state Medicaid agency.

Here is a summary of information we have gleaned from the Center for Medicare and Medicaid Services (CMS) Administrator Verma’s recent call.

CMS is implementing new rules and waivers that increase provider flexibility and free up resources to deal with a surge in COVID-19 patients. CMS is working with the provider community to provide clarity around specific changes that impact their operations.

  • The rulemaking process has been dramatically expedited to accommodate recent and forthcoming regulatory changes
  • CMS is in the process of working out details to administer CARES Act provisions, including further regulatory flexibilities, expansion of accelerated payment program, and $100 billion appropriated to reimburse eligible health care providers
  • CMS clarifies that the 3-Day Rule Waiver for skilled nursing facilities applies throughout the country and to all patients, regardless of their COVID-19 status

Medicaid Substance Use Disorder Treatment via Telehealth, and Rural Health Care and Medicaid Telehealth Flexibilities Guidance

This informational bulletin is composed of two parts: Rural Health Care and Medicaid Telehealth Flexibilities and Medicaid Substance Use Disorder Treatment via Telehealth.

  • The informational bulletin identifies opportunities for telehealth delivery for services to increase access to Medicaid services. It is composed of two parts, Rural Health Care and Medicaid Telehealth Flexibilities and Medicaid Substance Use Disorder (SUD) Treatment Services Furnished via Telehealth
  • The bulletin provides SUD guidance around Medication Assisted Treatment (MAT), counseling, high risk populations, and other areas critical to providing SUD services.

Long-Term Care Nursing Homes Telehealth and Telemedicine Tool Kit

CMS is issuing an electronic toolkit regarding telehealth and telemedicine for Long Term Care Nursing Home Facilities.

  • The toolkit includes electronic links to sources of information regarding telehealth and telemedicine, including the changes made by CMS over the last week in response to the national health emergency.
  • Much of the toolkit’s information is intended for providers who may wish to establish a permanent telemedicine program, but there is information here that will help in the temporary deployment of a telemedicine program as well.
  • There are specific documents identified that may be useful in choosing telemedicine vendors, equipment, and software, initiating a telemedicine program, monitoring patients remotely, and developing documentation tools. 


CMS makes regulatory changes to help US healthcare system address COVID-19 patient surge

CMS has issued a number of temporary regulatory waivers and new rules to assist the nation’s healthcare system with improved flexibility.

  • Increased hospital capacity. CMS will allow communities to take advantage of local ambulatory surgery centers that have canceled elective surgeries, per federal recommendations.
  • Healthcare workforce expansion. CMS’s temporary requirements allow hospitals and healthcare systems to increase their workforce capacity by removing barriers for physicians, nurses, and other clinicians to be readily hired from the local community as well as those licensed from other states without violating Medicare rules.
  • Paperwork requirements. CMS is temporarily eliminating paperwork requirements.
  • Telehealth in Medicare. CMS will now allow for more than 80 additional services to be furnished via telehealth.

Additional COVID-19 FAQs for state Medicaid and Children's Health Insurance Program (CHIP) agencies

CMS released an update to the COVID-19 FAQs posted on March 18, 2020 related to emergency preparedness and response, eligibility and enrollment flexibilities, benefit flexibilities, cost sharing flexibilities, financial flexibilities, managed care flexibilities, fair hearing flexibilities, health information exchange flexibilities, and COVID-19 T-MSIS coding guidance. Notably:

  • States that have CHIP disaster provisions in their state plans can activate these provisions. CMS considers a significant outbreak of an infectious disease to be a disaster. CMS also recommends that states that do not have disaster relief provisions in their CHIP state plans include language that a federal- or governor-declared emergency is considered an event that can trigger the disaster provisions.

States may not suspend use of their AVS, however CMS reminds states that they can rely on self-attestation of assets and verify financial assets using their AVS post-enrollment in Medicaid.

  • CMS can help provide technical assistance regarding approaches states can use to rapidly scale telehealth technologies.
  • CMS clarified and provided COVID-19 T-MSIS coding guidance.

For more information

We’re here to help. If you have more questions or want to have an in-depth conversation about your specific situation, please contact the team

Article
Takeaways from CMS national stakeholder call

Per CMS, all state Medicaid agencies, including territories, are eligible for the increased Federal Medical Assistance Percentage (FMAP), provided they adhere to the conditions outlined in the Families First Coronavirus Response Act (FFCRA). 

Key takeaways:

  • The increase in FMAP will be retroactive to January 1, 2020 and will be available to state Medicaid agencies through the end of the quarter in which the public health emergency for COVID-19 ends.
  • This guidance answers some of the following questions for states, including:
    • How long the funding will be available and when it begins
    • What costs are matchable under the enhanced funding 
    • The specific conditions under which states are eligible to claim the funds 
    • What documentation and processes will be needed in order to gain full access to funding

Trump administration releases COVID-19 checklists and tools to accelerate relief for state Medicaid & CHIP programs

In order to assist states as part of the COVID-19 outbreak, the Trump administration has released a number of tools and checklists that constitute a federal authority toolkit to support states in applying for and receiving federal waivers and other key flexibilities for their program. 

Key takeaways:
The tools released today include:

CMS issues FAQs on catastrophic health coverage and the coronavirus

A catastrophic health plan may not provide coverage of an essential health benefit prior to an enrollee meeting the deductible for that plan. In order to clarify treatment and coverage of COVID-19 for catastrophic health plans CMS has issued Frequently Asked Questions (FAQs).

Key takeaways:

  • Catastrophic plans currently include coverage for the diagnosis and treatment of COVID-19 as they must cover the essential health benefits (EHB) as required by the Patient Protection and Affordable Care Act (PPACA).
  • Issuers of catastrophic plans will be able to provide coverage for the diagnosis and treatment of COVID-19 for enrollees who have not yet met their deductible without CMS taking enforcing action.
  • The FAQ document encourages states to take an enforcement approach and CMS does not “consider a state to have failed to substantially enforce section 1302(e) of the PPACA if it takes such an approach.”

Relief for clinicians, providers, hospitals, and facilities participating in quality reporting programs in response to COVID-19

CMS is granting exceptions from reporting requirements and extensions for clinicians and providers participating in Medicare quality reporting programs.  

Key takeaways:

  • The exceptions include pending dates for measure reporting and data submission for related programs. 
  • For data submission deadlines in April and May of 2020, submission of those data will be optional, based on the facility’s choice to report.
  • 2019 data submission
    • Deadline extended from March 31, 2020 to April 30, 2020.
    • Deadlines for October 1, 2019 - December 31, 2019 (Q4) 
    • Data submission is optional for inpatient rehabilitation and hospital-acquired conditions.

CMS releases telehealth toolkits for general practitioners and End-Stage Renal Disease (ESRD) providers

CMS has released two toolkits on telehealth which follow the broadened access to Medicare telehealth services under the 1135 waiver authority and Coronavirus Preparedness and Response Supplemental Appropriations Act.

Key takeaways:

  • The toolkit consists of electronic links to sources of information pursuant to telehealth and telemedicine. 
  • Generally directed towards providers, particularly ones who may be considering a permanent telemedicine program.
  • CMS notes that most of the resources were established prior to the current COVID-19 crisis. As a result, there are likely references to rules and regulations whose requirements may have been waived for the duration of the outbreak.

Toolkits:

For more information

We’re here to help. If you have more questions or want to have an in-depth conversation about your specific situation, please contact the team

Article
New guidance regarding enhanced Medicaid funding for states

Here is a summary of information we have gleaned from recent CMS updates and guidance. 

COVID-19 stakeholder call - March 16 

CMS held a National Stakeholder Call on March 16, 2020 to update the healthcare community on the rapidly evolving COVID-19 situation, which was declared a national emergency by President Trump on March 13, 2020.

Key takeaways:

  • Administrator Verma reaffirmed the goal of reducing administrative barriers in the way of healthcare workers and agencies and to support them as best CMS is able.
  • Acknowledging that there were questions on testing, Administrator Verma outlined that there will be a ramp-up in testing in conjunction with state and local governments. 
  • CMS is relaxing clinician enrollment requirements for Medicare and making the same option available to states in their Medicaid programs.
  • The administration has been clear that it wants agencies to focus on infection control efforts. CMS is designing a streamlined template to evaluate infection control.
  • CMS sends guidance to Programs of All-Inclusive Care for the Elderly (PACE) Organizations.

On March 17, 2020, CMS issued guidance to all Programs of All-Inclusive Care for the Elderly (PACE) Organizations (POs) on accepted policies and standard procedures with respect to infection control.

Key takeaways:

  • POs will need to create, apply, and sustain a documented infection control plan that involves procedures to recognize, examine, regulate, and avert infections in PACE centers
  • POs will need to work to prevent infections within each participant’s place of residence, as well as implement procedures to record and develop corrective actions related to incidents of infection.
  • CMS provides guidance that recognizes POs may need to undertake strategies that do not traditionally comply with CMS PACE program requirements in order to provide benefits while guarding from COVID-19. Some examples of this may include telehealth services.
  • President Trump expands telehealth benefits for Medicare beneficiaries during COVID-19 outbreak.

CMS is expanding Medicare’s telehealth benefits under the 1135 waiver authority and the Coronavirus Preparedness and Response Supplemental Appropriations Act.

Key takeaways:

  • Under the new 1135 waiver, Medicare can pay for office, hospital, and other visits provided via telehealth across the country and including in patient’s place of residence starting March 6, 2020. 
  • Medicare telehealth visits: These visits are considered the same as in-person visits and are paid at the same rate as regular, in-person visits.
  • Virtual check-ins: Virtual check-in services can only be reported when the billing practice has an established relationship with the member.  
  • E-visits: Such services can only be reported when the billing practice has an established relationship with the patient.  

CMS coronavirus partner virtual toolkit

CMS has released a virtual toolkit to help stakeholders stay up-to-date on CMS materials available on COVID-19. Here is specific guidance from the toolkit designed for states and health plans:

CMS approves first state request for 1135 Medicaid waiver in Florida and Washington

The 1135 waiver allows Florida and Washington to modify certain Medicaid program requirements, policies, operational procedures, and deadlines applicable to each state’s administration of its Medicaid program during the period of the national state of emergency to prevent further transmission of COVID-19. 

Key takeaways from Florida’s waiver

  • Provider participation flexibilities for Medicaid and CHIP Waiver of Service Prior Authorization (PA) Requirements for fee-for-service delivery systems
  • Waiver for Pre-Admission Screening and Annual Resident Review (PASRR) Level II Level II Assessments for 30 Days
  • Waiver to allow evacuating facilities to provide services in alternative settings, such as a temporary shelter when a provider’s facility is inaccessible
  • Waiver to temporarily delay scheduling for state fair hearing requests and appeal deadlines (NOTE: CMS was unable to waive all of Florida’s requested authorities in this area)

If you have questions or would like more information, we are here to help. Please contact us

Article
CMS update for the healthcare community: Our takeaways

Read this if you are a State Medicaid Director, State Medicaid Chief Information Officer, State Medicaid Project Manager, or State Procurement Officer—or if you work on a State Medicaid Enterprise System (MES) certification effort.

On October 24, 2019, the Centers for Medicaid and Medicare Services (CMS) published the Outcomes-Based Certification (OBC) guidance for the Electronic Visit Verification (EVV) module. Now, CMS is looking to bring the OBC process to the rest of the Medicaid Enterprise. 

The shift from a technical-focused certification to a business outcome-focused approach presents a unique opportunity for states as they begin re-procuring—and certifying—their Medicaid Enterprise Systems (MES).

Once you have defined the scope of your MES project—and know you need to undertake CMS certification—you need to ask “what’s next?” OBC can be a more efficient certification process to secure Federal Financial Participation (FFP).

What does OBC certification entail?

Rethinking certification in terms of business outcomes will require agencies to engage business and operations units at the earliest possible point of the project development process to define the program goals and define what a successful implementation is. One way to achieve this is to consider MES projects in three steps. 

Three steps to OBC evaluation

Step 1: Define outcomes

The first step in OBC planning seems easy enough: define outcomes. But what is an outcome? To answer that, it’s important to understand what an outcome isn’t. An outcome isn’t an activity. Instead, an outcome is the result of the activity. For example, the activity could be procuring an EVV solution. In this instance, an outcome could be that the state has increased the ability to detect fraud, waste, and abuse through increased visibility into the EVV solution.

Step 2: Determine measurements

The second step in the OBC process is to determine what to measure and how exactly you will measure it. Deciding what metrics will accurately capture progress toward the new outcomes may be intuitive and therefore easy to define. For example, a measure might simply be that each visit is captured within the EVV solution.

Increasing the ability to detect fraud, waste, and abuse could simply be measured by the number of cases referred to a Medicaid fraud unit or dollars recovered. However, you may not be able to easily measure that in the short-term. Instead, you may need to determine its measurement in terms of an intermediate goal, like increasing the number of claims checked against new data as a result of the new EVV solution. By increasing the number of checked claims, states can ensure that claims are not being paid for unverified visits. 

Step 3: Frequency and reporting

Finally, the state will need to determine how often to report to measure success. States will need to consider the nuances of their own Medicaid programs and how those nuances fit into CMS’ expectations, including what data is available at what intervals.

OBC represents a fundamental change to the certification process, but it’s important to highlight that OBC isn’t completely unfamiliar territory. There is likely to be some carry-over from the certification process as described in the Medicaid Enterprise Certification Toolkit (MECT) version 2.3. The current Medicaid Enterprise Certification (MEC) checklists serve as the foundation for a more abbreviated set of criteria. New evaluation criteria will look and feel like the criteria of old but are likely to be a fraction of the 741 criteria present in the MECT version 2.3.

OBC offers several benefits to states as you navigate federal certification requirements:

  1. You will experience a reduction in the amount of time, effort, and resources necessary to undertake the certification process. 
  2. OBC refocuses procurement in terms of enhancements to the program, not in new functions. Consequently, states will also be able to demonstrate the benefits that each module brings to the program which can be integral to stakeholder support of each module. 
  3. Early adoption of the OBC process can allow you to play a more proactive role in certification efforts.

Continue to check back for a series of our project case studies. Additionally, if you are considering an OBC effort and have questions, please contact our team. You can read the OBC guidance on the CMS website here
 

Article
Three steps to outcomes-based certification

As the Project Management Body of Knowledge® (PMBOK®) explains, organizations fall along a structure and reporting spectrum. On one end of this spectrum are functional organizations, in which people report to their functional managers. (For example, Finance staff report to a Finance director.) On the other end of this spectrum are projectized organizations, in which people report to a project manager. Toward the middle of the spectrum lie hybrid—or matrix—organizations, in which reporting lines are fairly complex; e.g., people may report to both functional managers and project managers. 

Problem: Weak Matrix Medicaid System Vendors

This brings us to weak matrix organizations, in which functional managers have more authority than project managers. Many Medicaid system vendors happen to fall into the weak matrix category, for a number of different reasons. Yet the primary factor is the volume and duration of operational work—such as provider enrollment, claims processing, and member enrollment—that Medicaid system vendors perform once they exit the design, development, and implementation (DDI) phase.

This work spans functional areas, which can muddy the reporting waters. Without strong and clear reporting lines to project managers, project success can be seriously (and negatively) affected if the priorities of the functional leads are not aligned with those of the project. And when a weak matrix Medicaid system vendor enters a multi-vendor environment in which it is tasked with implementing a system that will serve multiple departments and bureaus within a state government, the reporting waters can become even muddier.


Solution: Using a Project Management Office (PMO) Vendor

Conversely, consulting firms that provide Project Management Office (PMO) services to government agencies tend to be strong matrix organizations, in which project managers have more authority over project teams and can quickly reallocate team members to address the myriad of issues that arise on complex, multi-year projects to help ensure project success. PMOs are also typically experienced at creating and running project governance structures and can add significant value in system implementation-related work across government agencies.

Additional benefits of a utilizing a PMO vendor include consistent, centralized reporting across your portfolio of projects and the ability to quickly onboard subject matter expertise to meet program and project needs. 
For more in-depth information on the benefits of using a PMO on state Medicaid projects, stay tuned for my second blog in this series. In the meantime, feel free to send your PMO- or Medicaid-related questions to me
 

Article
The power of the PMO: Fixing the weak matrix

Law enforcement, courts, prosecutors, and corrections personnel provide many complex, seemingly limitless services. Seemingly is the key word here, for in reality these personnel provide a set number of incredibly important services.

Therefore, it should surprise no one that justice and public safety (J&PS) IT departments should also provide a well-defined set of services. However, these departments are often viewed as parking lots for all technical problems. The disconnect between IT and other J&PS business units often stems from differences in organizational culture and structure, and differing department objectives and goals. As a result, J&PS organizations often experience misperception between business units and IT. The solution to this disconnect and misperception? Defining IT department services.

The benefits of defined IT services

  1. Increased business customer satisfaction. Once IT services align with customer needs, and expectations are established (e.g., service costs and service level agreements), customers can expect to receive the services they agreed to, and the IT department can align staff and skill levels to successfully meet those needs.
  2. Improved IT personnel morale. With clear definition of the services they provide to their customers, including clearly defined processes for customers to request those services, IT personnel will no longer be subject to “rogue” questions or requests, and customers won’t be inclined to circumvent the process. This decreases IT staff stress and enables them to focus on their roles in providing the defined services. 
  3. Better alignment of IT services to organizational needs. Through collaboration between the business and IT organizations, the business is able to clearly articulate the IT services that are, and aren’t, required. IT can help define realistic service levels and associated services costs, and can align IT staff and skills to the agreed-upon services. This results in increased IT effectiveness and reduced confusion regarding what services the business can expect from IT.
  4. More collaboration between IT and the organization. The collaboration between the IT and business units in defining services results in an enhanced relationship between these organizations, increasing trust and clarifying expectations. This collaborative model continues as the services required by the business evolve, and IT evolves to support them.
  5. Reduced costs. J&PS organizations that fail to strategically align IT and business strategy face increasing financial costs, as the organization is unable to invest IT dollars wisely. When a business doesn’t see IT as an enabler of business strategy, IT is no longer the provider of choice—and ultimately risks IT services being outsourced to a third-party vendor.

Next steps
Once a J&PS IT department defines its services to support business needs, it then can align the IT staffing model (i.e., numbers of staff, skill sets, roles and responsibilities), and continue to collaborate with the business to identify evolving services, as well as remove services that are no longer relevant. Contact us for help with this next step and other IT strategies and tactics for justice and public safety organizations.

Article
The definition of success: J&PS IT departments must define services

If you’ve been tasked with leading a high-impact project for your organization, you may find managing the scope, budget and schedule is not enough to ensure project success—especially when you encounter resistance to change. When embarking on large-scale change projects spanning people, processes and technology, appointing staff as “coaches” to help support stakeholders through the change—and to manage resistance to the change—can help increase adoption and buy-in for a new way of doing things.

The first step is to identify candidates for the coaching role. These candidates are often supervisory staff who have credibility in the organization—whether as a subject matter expert, through internal leadership, or from having a history of client satisfaction. Next, you need a work plan to orient them to this role. One critical component is making sure the coaches themselves understand what the change means for their role, and have fully committed before asking them to coach others. They may exhibit initial resistance to the change you will need to manage before they can be effective coaches. According to research done by Prosci®, a leading change management research organization, some of the most common reasons for supervisor resistance in large-scale change projects are:

  • Lack of awareness about and involvement in the change
  • Loss of control or negative impact on job role
  • Increased work load (i.e., lack of time)
  • Culture of change resistance and past failures
  • Impact to their team

You should anticipate encountering these and other types of resistance from staff while preparing them to be coaches. Once coaches buy into the change, they will need ongoing support and guidance to fulfill their role. This support will vary by individual, but may be correlated to what managerial skills they already possess, or don’t. How can you focus on developing coaching skills among your staff for purposes of the project? Prosci® recommends a successful change coach take on the following roles:

  • Communicator—communicate with direct reports about the change
  • Liaison—engage and liaise with the project team
  • Advocate—advocate and champion the change
  • Resistance manager—identify and manage resistance
  • Coach—coach employees through the change

One of the initial tasks for your coaches will be to assess the existing level of change resistance and evaluate what resistance you may encounter. Prosci® identifies three types of resistance management work for your coaches to begin engaging in as they meet with their employees about the change:

  • Resistance prevention―by providing engagement opportunities for stakeholders throughout the project, building awareness about the change early on, and reinforcing executive-level support, coaches can often head off expected resistance.
  • Proactive resistance management―this approach requires coaches to anticipate the needs and understand the characteristics of their staff, and assess how they might react to change in light of these attributes. Coaches can then plan for likely forms of resistance in advance, with a structured mitigation approach.
  • Reactive resistance management―this focuses on resistance that has not been mitigated with the previous two types of resistance management, but instead persists or endures for an extended amount of time. This type of management may require more analysis and planning, particularly as the project nears its completion date.

Do you have candidates in your organization who may need support transitioning into coaching roles? Do you anticipate change resistance among your stakeholders? Contact us and we can help you develop a plan to address your specific challenges.

Article
How to identify and prepare change management coaches